road closed

Road Closure

Subject to weather, starting January 4th Blue Nile will close Wornall Road between 133rd Street and 135th Street so they may complete work on a section of the new water main running north and south. Road closure signs will be posted at Blue Ridge and Wornall Road to provide ample notice of road closure. Trucks will not be permitted to cut through the Village Glenn neighborhood.

The City asks all businesses to plan accordingly for the street closure.  The 135th Street and Wornall Road intersection closure is scheduled for the entire month of January.  Traffic along 135th Street will not be impacted by the construction activities.

Water Main Installation

Blue Nile has completed the installation of the new water main along 135th Street.  The first week of January, Blue Nile will complete connecting individual property service lines to the new main.  These lines are located along 135th Street within the construction zone.

Storm Water System

In January, J.M. Fahey will commence the construction of the new storm water system along 135th Street.  At this time, this construction work does not anticipate to impact traffic along 135th Street.

Please visit our construction page to learn more about the development in Martin City!