Construction Update: February 2016

martincityconstruction

Water Main Installation: Blue Nile has completed the majority of their work to install the new water main along 135th Street.  Additional water construction will be scheduled at a later time. Storm Water System: Subject to weather, J.M. Fahey will commence the construction of the new storm water system along 135thStreet.  At this time, this […]

Construction Update – December 2015

BlueNile

Water Main Installation Blue Nile anticipates completing the majority of  the installation of the new water main by December 6, 2015. Upon the completion of the installation, Water Services will run tests on the system during the week. Subject to the water main passing all tests, Blue Nile will begin the week of December 14th […]