Category: Construction

Construction Update: February 2016
Post

Construction Update: February 2016

Water Main Installation: Blue Nile has completed the majority of their work to install the new water main along 135th Street.  Additional water construction will be scheduled at a later time. Storm Water System: Subject to weather, J.M. Fahey will commence the construction of the new storm water system along 135thStreet.  At this time, this...

Construction Update: January 2016
Post

Construction Update: January 2016

Road Closure Subject to weather, starting January 4th Blue Nile will close Wornall Road between 133rd Street and 135th Street so they may complete work on a section of the new water main running north and south. Road closure signs will be posted at Blue Ridge and Wornall Road to provide ample notice of road...

Construction Update: November 2015
Post

Construction Update: November 2015

Construction has commenced in Phase 2 of the 135th Street Public Improvements (Oak Street to Wornall Road). The construction schedule is subject to change depending on weather, unforeseen construction matters, or schedules accommodating business operations. The typical construction schedule is 7:00 a.m. to 5:30 p.m. Monday –Thursday, unless noted otherwise (i.e. water main construction on...

August 2015 Construction Update
Post

August 2015 Construction Update

Phase 1 Construction Update: This spring and summer rain has made us very grateful for the new 66” storm water line installed in Phase 1 of the 135th Street Public Improvement Project! Unfortunately, due to the rain, the City’s contractor has been delayed in their efforts to re-stripe the street and on-street parking stalls between...

Construction Update – July 2015
Post

Construction Update – July 2015

Phase 1 Construction Update: July will be a busy month for construction activity along 135th Street within Phase 1 of the public improvement project. (The work should not impact traffic flow along 135th Street.)  The City’s contractor will be finishing up odds and ends on the City’s construction punch list.  All work is subject to...

April 2015 Construction Update
Post

April 2015 Construction Update

Are there any plans to build additional sidewalks along 135th Street? YES! New sidewalks will be built in Phase 2 of the public improvements along 135th Street. On the south side of 135th street, the new sidewalk will begin in front of KC Running Company and go west to approximately the west property line of Martin...

March 2015 Construction Update
Post

March 2015 Construction Update

135th Street Public Improvements Construction Update: Phase 1– During the last part of March and first of April, the City’s contractors will be working along 135th Street to finish punch list items within Phase 1. Phase 2– At the City Appreciation Breakfast in February, 6th District Council members shared the proposed Fiscal Year ’16 City...

Construction Update January 2015
Post

Construction Update January 2015

The City of Kansas City Missouri’s Water Service Department continues their work on the installation of a new water main along Holmes Road between Blue Ridge Boulevard and 135th Street. Over the next few months, the CID will have a contractor working in sections along Phase 1 of 135th Street.  The contractor will be installing...

Construction Update – December 2014
Post

Construction Update – December 2014

Blue Nile Contractors continue to work on the water main replacement along Holmes from Blue Ridge Boulevard to the north side of 135th Street. In November, the Contractor complete a portion of the work along Blue Ridge. The contractual completion date for all work is January 2015 but the Contractor is hopeful work along Holmes...